The Order of Work That Decides a Bathroom Renovation

Need it done, not just explained? Turnkey renovation contractors in Beirut - Every trade under one contract.

A bathroom is the smallest room in the apartment and the most expensive square metre in it. Everything that can go wrong in a building — water, drainage, ventilation, electricity, structure — meets inside four walls, and most of the work that determines whether it lasts is buried before the tiles go on.

The short version
  • The waterproofing membrane and the fall of the floor decide whether the room survives; everything else is finish.
  • Moving the drain is the single decision that most changes the shape of the job.
  • Sequence matters more than product choice — good tiles laid on bad preparation still fail.
  • Ask to see the room flooded and tested before a single tile is laid.

We are writing this from the site side. The bathrooms we get called back to fix are almost never failing because someone chose the wrong tile. They fail because a step was skipped in the two weeks before anyone saw anything pretty.

Waterproofing membrane applied to a bathroom floor and wall junction before tiling
The layer that decides everything. Once tiles are down, nobody can inspect this again without demolition.

What actually drives the scope

Before anyone can describe the work, four questions have to be answered. Each one moves the job into a different category, and the difference between them is far larger than the difference between a mid-range tile and a premium one.

DecisionIf you keep it as isIf you change it
Drain and stack positionDemolition stays shallow, the floor build-up stays thin, the schedule stays short.You are into the floor slab, re-grading falls, and coordinating with the building stack. Different job entirely.
Wall layoutExisting services stay where they are; chasing is minimal.Every pipe and cable behind those walls has to be re-run and re-tested.
VentilationWhatever the building gave you, with its existing humidity behaviour.A dedicated extract path — the difference between a bathroom that stays dry and one that grows mould in year two.
Waterproofing extentA patched membrane inherits the previous installer’s mistakes.A full new membrane, floor to shower height and beyond, tested before tiling.
The most common false economy
Keeping old waterproofing because the tiles above it looked fine. Membranes fail silently at junctions and penetrations, and the first visible sign is usually damp on a neighbour’s ceiling. If the room is being stripped anyway, the membrane is the last place to save.

The sequence, in order

A bathroom is not built in parallel. Each stage has to be complete and checked before the next one covers it. This is the order we work in, and the order any serious contractor should be able to recite without looking at notes.

  1. Protection and isolation

    Water to the unit is isolated, the stack is protected, and the route from the door to the building exit is covered. Debris in a Beirut stairwell is how you lose the building committee.

  2. Strip out

    Fixtures, tiles and screed come out down to the structural slab. This is when you find out what the previous renovation actually did.

  3. First fix plumbing

    Supply and drainage are re-run to the new layout, with falls set on the drainage. Everything is pressure-tested while it is still visible.

  4. First fix electrics

    Circuits, lighting points, extract fan, water heater feed and any heated element are pulled through and terminated safely. Zones around water are respected.

  5. Ventilation

    The extract path is formed and ducted out — not into a ceiling void. This is the stage most commonly skipped and most commonly regretted.

  6. Screed and falls

    The floor is built back up with the fall running to the drain. A level bathroom floor is a design fault, not a neutral choice.

  7. Waterproofing

    Primer, membrane, reinforcement at every corner, junction and penetration, taken up the walls to full shower height and across the whole floor.

  8. Flood test

    The room is blocked and flooded, then left. This is your one chance to prove the membrane before it disappears. Insist on it.

  9. Tiling

    Walls and floor, set out so that cuts land where they are least visible and the drain sits cleanly in the pattern.

  10. Grout and seal

    Grout after the adhesive has properly cured, then flexible sealant at every movement junction — floor to wall, wall to wall, around the tray.

  11. Second fix

    Sanitaryware, taps, screen, mirror, lighting, accessories. Fast and visible, which is why people think this is the renovation.

  12. Commissioning

    Every outlet run, every drain checked under load, the extract measured, silicone inspected, then a snag list walked with you.

If a contractor cannot tell you when the flood test happens, he is not planning to do one.

BaytiFix site supervision

Old Beirut buildings have their own rules

Much of the housing stock in Beirut, Achrafieh, Hamra and Ras Beirut predates any modern plumbing standard. That creates a predictable set of complications worth knowing before you plan.

  • Cast iron stacks that are shared vertically — cutting into one affects the neighbours above and below, so timing has to be agreed.
  • Original screeds that hide previous, undocumented alterations. Assume at least one surprise.
  • Slab thickness that limits how far a drain can be moved without building up the floor.
  • Building water pressure that depends on a shared pump and roof tank, which changes what shower fittings will actually perform.
  • Access — narrow stairwells and small lifts decide what size of slab or tray can physically reach your floor.
Large-format tiling and marble work in a completed bathroom
Finish quality is judged at the edges: how cuts land at corners, how the drain sits in the pattern, how joints line up between floor and wall.

What separates the quotes you will receive

Two contractors can describe the same bathroom in completely different ways. The way to compare them is not to look at a single figure, but to check whether the same items exist in both documents.

ItemA vague quote saysA serious quote says
Demolition“Strip out bathroom.”Down to which layer, what is retained, where debris goes, how the stairwell is protected.
WaterproofingNot mentioned, or one word.Named system, coverage area, height up the walls, reinforcement detail, flood test included.
Drainage“Plumbing works.”Whether the drain moves, what falls are set, how the stack connection is made and tested.
VentilationSilent.Extract type, duct route, termination point.
Tiling“Supply and fix tiles.”Setting-out plan, format, adhesive type, grout and movement joint locations.
ResponsibilityUnclear.Who supplies what, what the guarantee covers, how long it runs, what voids it.
One question that reveals a lot
Ask: “What will you do if the slab is thinner than expected once you open the floor?” A contractor who has done this before will answer with options and consequences immediately. A guess sounds like a guess.

Choosing materials that suit the room

Bathrooms punish materials that were chosen for a showroom rather than a wet, humid, frequently cleaned space. A few practical rules survive every trend cycle.

  • Floor tiles need a slip rating suitable for wet feet — polished marble on a shower floor looks superb and behaves badly.
  • Large formats mean fewer grout lines but demand a flatter substrate; on an uneven old floor they expose every deviation.
  • Natural stone is porous and needs sealing and pH-neutral cleaning; porcelain is inert and forgiving.
  • Matte finishes hide water spotting far better than gloss in a building with hard water.
  • Fittings should match the actual pressure your building delivers, not the pressure the catalogue assumes.

For the full flat renovation sequence that a bathroom sits inside, see the turnkey renovation guide. For the waterproofing and tiling work itself, see waterproofing and tiling & marble.

How long does a bathroom renovation take?

A finish-level refresh where nothing moves is measured in days. A full strip-out with relocated drainage, new waterproofing and a flood test is measured in weeks, because curing and testing time cannot be compressed.

Can I renovate one bathroom while living in the flat?

Yes if there is a second bathroom and the building allows water isolation on a schedule. With a single bathroom it is possible but genuinely disruptive, and worth planning around.

Do I really need a flood test?

It is the only proof you will ever get that the membrane works. It costs a day. Repairing a failed membrane after tiling costs the whole room.

What about the neighbours below?

Tell them before you start, not after. Any leak that appears in the weeks after a bathroom job will be attributed to it, so having a documented, witnessed flood test protects you as much as them.

Is it worth moving the toilet?

Only if the new layout genuinely improves how the room works. It is the most expensive centimetre of movement in the whole renovation, because it means opening the floor and re-grading drainage.